Процесс сверления отверстий
Время выпуска:
2020-05-06
CrawlerRigIn the process of drilling into the hole, according to the formation, hole depth changes, reasonable selection of drilling parameters and bit, timely modulation of mud, to ensure the quality of the hole. When entering the sand layer and pebble layer, the footage speed should be appropriately slowed down, the consistency of the mud should be improved, and the footage of each drilling return should be reduced to ensure the stability of the hole wall. During drilling construction, the front shovel shall be used to remove the drilling slag in time to ensure the site is clean and tidy, which is conducive to the next construction. After the drilling reaches the required hole depth and the drilling is stopped, pay attention to maintain the slurry surface elevation of the mud in the hole to ensure the stability of the hole wall.
1. Mud preparation
Яма грязи (включая танк седиментирования для возвращения слурры и танка запаса грязи) установила на месте вообще 1. 5 ~ 2. 0 раз больше объема скважины, и он должен иметь лучшую способность к просачиванию. Зона навоза устанавливается рядом с отстойником, а осадок очищается с помощью экскаватора-экскаватора и помещается в зону навоза, чтобы обеспечить странствующее пространство и место для хранения грязи. Существует два вида оборудования для подготовки грязи, один-смеситель грязи, а другой-гидравлический смеситель. При использовании порошка глины для того чтобы сделать слурры, самое лучшее использовать гидравлический смеситель; при использовании бентонита для того чтобы сделать слурры, используйте смеситель грязи. Регенерационная обработка грязи для защиты стен: в строительстве принят метод удаления шлака гравитационным седиментацией, I. E. метод использования разницы относительной плотности между грязью и почвенным шлаком для осаждения почвенного шлака для удаления почвенного шлака. Рекуперационная грязевая яма устанавливается на месте для использования в качестве защитной грязи для стен. После того, как грязь очищается осаждением, она транспортируется в резервуар для хранения суспензии и дополнительно обрабатывается в резервуаре для хранения суспензии (добавляя соответствующее количество кальцинированной соды и КМЦ для улучшения характеристик грязи) и повторно используется после прохождения теста.
2. Buried casing
После того, как свайный фундамент расположен, четыре контрольных сваи помещаются поперечными гвоздями в соответствии с точками позиционирования сваи, а стальной корпус похоронен на основе четырех контрольных свай. Для того чтобы защитить отверстие от обрушения и сформировать напор воды и располагая проводника в отверстии, захоронение кожуха ключ в роторной деятельности раскопок. Кожух сваи изготовлен из стальной пластины толщиной 10 мм. Внутренний диаметр свайного кожуха составляет 20 см, а высота-2,0 м. В верхней части открываются два перелива. Когда кожух кучи похоронен, он завершен ручным и механическим сотрудничеством. Верхняя часть кожуха кучи главным образом отжата в почву путем ведра буровой установки роторного. Верхняя часть свайной обсадной колонны должна быть на 20 см выше земли и оставаться горизонтальной. Глубина погребения составляет 1,8 м. Отклонение между центром обсадной колонны и центром обсадной колонны не должно превышать 50 мм. Кожух должен быть похоронен вертикально, а скорость наклона должна составлять менее 1,5%.

3. Drilling positioning
The drilling rig can only be in place on the basis that the pile position is checked correctly, the casing is buried in line with the requirements, and the casing and floor elevation have been measured. The positioning of the pile crane shall be accurate, horizontal, vertical and stable, and the center line of the drilling rig guide rod, the center line of the swivel plate and the center line of the casing shall be kept in the same straight line. After the rotary drilling rig is in place, its verticality shall be adjusted by the automatic control system. When the drilling rig is placed and positioned, the base shall be flat, the tower shall be vertical, the center of the rotary table (drill bit) shall be aligned with the center of the cross line of the casing, and the drilling shall be carried out after the stable liquid is injected.
4. Drilling into the hole
Before hole formation, check the diameter of the drill bit, the wear of the drill bit, and replace the drill bit in time if the wear exceeds the standard during construction; correctly select the shape, specification and angle of the cutting teeth at the bottom of the drill bucket according to the soil layer condition; calculate the pile bottom elevation according to the pile casing elevation, pile top design elevation and pile length, so as to control it during drilling.
5. Hole-forming
Конструкция будет унесена согласно параметрам определенным в конструкции сваи теста, и полный рабочий день рекордер будет настроен для того чтобы записать различные параметры отверстия-формируя процесс, как добавление бурильной трубы, сверля глубина, геологические особенности, механическое повреждение оборудования, препоны, етк. Записи должны быть аккуратными, своевременными, Точный и ясный. Во время сверля процесса, скорость отснятого материала будет проконтролирована согласно геологохимическим условиям: сверля от трудного образования к мягкому образованию, сверля скорость можно соотвественно ускорить ход; когда мягкое образование будет трудным образованием, замедляет и продвигает медленно; в образовании легком для того чтобы сжать диаметр, Количество подметания отверстий должно быть соответствующим образом увеличено, чтобы предотвратить усадку; для твердого пластикового слоя должно быть принято быстрое бурение для повышения эффективности бурения; для песчаного слоя должно быть принято медленное бурение, а вес и вязкость грязи должны быть соответствующим образом увеличены. Когда буровая установка находится на месте, она должна быть плоской, стабильной и не наклонной. Для того чтобы точно контролировать глубину отверстия, будет обеспечена веревочка провода измеряя 100 метров после проверки, и автоматический регистратор глубины будет наблюдаться для наблюдения и записи во время конструкции.
6. Hole bottom sedimentation control
Режущий и подъемный механизм роторного бурового ковша полностью отличается от режущей и подъемной формы формирования положительного и обратного циркуляционного отверстия при общем роторном бурении. Бывший отрезать ненарушенную почву на дне отверстия в прокладки через сверля ведро и нагрузить его в сверля ведро для подниматься и раскопанный, пока латтер сломать ненарушенную почву на дне отверстия через буровой наконечник и раскопанный поясом циркуляции грязи. Нижняя поверхность первого медленная, возмущение почвы, вызванное бурением до проектной высоты, очень мало, и нет полисилтинговой воронки. Поэтому, управление стабилизированной жидкости должно быть усилено, твердое содержание должно быть проконтролировано, выкостность должна быть увеличена, быстрое высыпание должно быть предотвращено, и роторное выкапывая количество 2 сверля ведер перед окончательным отверстием должно быть проконтролировано. После того как отверстие-формируя глубину соотвествует конструкции, буровая установка будет смещена и окончательное принятие отверстия будет унесено как можно скорее. От остановки очистки отверстия до начала заливки бетона его следует контролировать в течение 1,5-3 часов, как правило, не более 4 часов, в противном случае отверстие следует снова очищать. Метод конструкции роторной пробуренной кучи имеет преимущества надежного качества конструкции, быстрой отверстие-формируя скорости, высокого отверстие-формируя тарифа, сильной приспособляемостьи, значительно сокращая период строительства, меньше ненужного загрязнения слурры, малошумных и низких, защищая окружающую среду, преодоление недостатков большего количества ила на дне ямы, Низкое сопротивление трению стороны кучи и плохое управление грязью во время механического отверстия-формировать, и значительно улучшающ качество конструкции. Хотя первая входная стоимость велика, экономические и технические показатели, такие как потребление затрат на формирование отверстий, ниже, чем другие методы затрат на формирование отверстий, это идеальный процесс строительства, по сравнению с другими процессами, всестороннее рассмотрение заключается в снижении стоимости.